Abstract:According to the construction and management practice, pumping station’s features in reconstruction was introduced; key points that should be considered in each step was also proposed. In the earlier stage, focus should be put on construction item and detection of electromechanical equipments, in the primaryd esigns tage,t hep roject design parameters’rechecka ndt ypes’selectioni s especiallyi mportant; int he constructions tage,s trictly carryingo utc onstructionp rocedure ist he focus, purchasinga nd install ofe quipments is also of great importance; in the final, the key becomes the financial audit work and to archive all kind of materials ofp roject’sc hecka nda ccept.
汤汉志. 泵站技术改造工程建设要把好“四关”[J]. 排灌机械工程学报, 2005, 23(3): 49-51.
TANG Han-zhi. Four Keys for the Pumping Station’s Reconstruction. Journal of Drainage and Irrigation Machinery Engin, 2005, 23(3): 49-51.