Comparison of power generation scheme and benefit analysis for pump units in Jiangdu No.3 Pumping Station in reverse mode |
WEI Qiang-Lin1, HAN Yong-Geng1, CHOU Bao-Yun2, HE Shu-Quan2 |
(1. Jiangdu Water Conservancy Project Bureau of Jiangsu Province, Yangzhou, Jiangsu 225200, China; 2. School of Energy and Power Engineering, Yangzhou University, Yangzhou, Jiangsu 225127, China) |
|
|
Abstract Jiangdu No.3 Pumping Station is located at the source of East Route of SouthtoNorth Water Diversion Project.
The station is subject to amount of redundant water from the upper reach, so it can utilize the water to generate power; however, the time for pumping water is much longer than that for generating power. Considering those features, it is necessary to optimize the power generation scheme for this reversible pump unit. In doing so, the basic situation and benefits of power generated by the pump unit in reverse mode were introduced; the technical issues were analyzed and the economic benefits were compared when the pump unit is reverse mode. The benefits of the pumping station due to power generation in the past more than 3 years were summarized, and the net benefits of three power generation schemes were analyzed and compared from the relationship between investment and income. The results indicated that large pumping station generating power by exploiting redundant water from upper reach can achieve better economic and social benefits. However, if a pumping station can be used to generate power or not and what scheme will be adopted should depend on the consideration about the primary and secondary relationship between pumping water and power generation as well as the economic and social benefits. For Jiangdu No.3 Pumping Station, the initial power generation equipment was updated to frequency converters. Though the frequency converters were installed, the cost of the main electric motors was reduced, causing the total cost of equipments was decreased. As a result, the power output was increases by 30%-35%. Besides, the frequency converters have no influence on the pumping efficiency of pump units, so they are technologically feasible. Moreover, the frequency converters are reliable in operation and can be installed easily.
|
Received: 16 February 2012
Published: 10 April 2012
|
|
|
|
参考文献(References)[1]钱钧,邵正荣.现代化大型泵站与南水北调东线工程的设计与研究[J].排灌机械,2003,21(2):1-6.Qian Jun, Shao Zhengrong. Design and research on modern largesized scale pumping station and the SouthtoNorth Water Transfer Project in the East of China[J]. Drainage and Irrigation Machinery, 2003, 21(2):1-6.(in Chinese)[2]王锋,姜建国.基于四象限高压变频技术的泵站反向发电方式研究[J].水力发电学报,2011,30(5):218-221,230.Wang Feng, Jiang Jianguo. Study on the mode of pumping station generators based on fourquadrants medium converter[J]. Journal of Hydroelectric Engineering, 2011, 30(5): 218-221, 230.(in Chinese)[3]莫岳平,黄海田,周济人.轴流泵站反向发电运行方式选择的研究[J].扬州大学学报,1999,2(2):1-6.Mo Yueping,Huang Haitian, Zhou Jiren. The research of inverted power generation operation way for axis pumping station[J]. Journal of Yangzhou University,1999, 2(2): 1-6.(in Chinese)[4]问泽杭,莫兆祥.变频发电技术在刘老涧泵站反向发电中的应用[J].人民长江,2009,40(20):53-55.Wen Zehang, Mo Zhaoxiang. The application of variable frequency power generation technology in reverse power of Liulaojian pumping station[J]. Yangtz River, 2009,40(20):53-55.(in Chinese)[5]刘大凯.水轮机[M]. 3版.北京:中国水利水电出版社,1997.[6]刘宁,汪易森,张纲.南水北调工程水泵模型同台测试[M].北京:中国水利水电出版社, 2006.[7]冯晓莉,仇宝云,杨兴丽,等.大型泵站运行优化方法及其应用[J].排灌机械工程学报,2011,29(2):127-132.Feng Xiaoli, Qiu Baoyun, Yang Xingli, et al. Optimal methods and its application of large pumping station operation [J]. Journal of Drainage and Irrigation Machinery Engineering, 2011,29(2):127-132.(in Chinese)[8]陈守伦.工程经济[M]. 南京:河海大学出版社,1996. |
|
|
|