Analyse of Trying Running After Technological Transformation of JianBi Pumping Station |
XU Fu-xiang |
JianBi Pumping Station, Zhenjiang 212003, China |
|
|
Abstract After flood season of 2003 before flood season of 2005. The Jian Bi Pumping Station has transformed the capital equipment the article brief introduction the transform situation and key introduction running situation of trying on of equipment after transform.Have analyse that has tried question and counter measure appearing in course out and offered the suggestion of improving further. The reconstruction of pumping station is proved successful through analsysizing its economic profit and try out summary.
|
Received: 08 August 2013
|
|
|
|
[1] 刘超,汤方平,袁家博.大型轴流泵站主泵改型研究与应用[J].排灌机械,2002,20(3):12-16[2] 周君亮.泵站建设中装置选用问题[J].排灌机械,2001,19(1):3-12[3] 林建时,李明俊.镇江市谏壁抽水站技术改造探讨[J].排灌机械,2001,19(5):24-27 |
|
|
|