Abstract:The performance of the thrust bearing bush of the main motor in a large vertical pump unit was studied,and the cause of burnout malfunction of the main motor thrust bush in No.4 Pumping Station of Jiangdu Hydro-junction was analyzed.A thrust bearing bush with elastically metallic plastics as a substitute for babbit alloy was used for the structure imrovement in the main motor.According to the application of the elastically metallic plastic thrust bush,and by comparison with the babbit thrust bush,the special attention for the application of the elastically metallic plastic thrust bush was introduced.Through 20 000 hours safe operation,wear extent of the plastic bush was less than 0.05 mm.At the same time,the main pump unit operated steadily;its plastic bush temperature was held at about 30 ℃ and its cooling water temperature kept around 20 ℃.Therefore,the design improvement adopting the plastic bush could ultimately decrease the probability of the burnout trouble.
孙明权, 仇宝云, 阚永庚. 大型立式水泵机组推力瓦性能分析及改进设计[J]. 排灌机械工程学报, 2009, 27(2): 129-133.
Sun Mingquan,Qiu Baoyun,Kan Yonggeng. Performance analysis and design improvement of thrust bearing bush in a large vertical pump unit . Journal of Drainage and Irrigation Machinery Engin, 2009, 27(2): 129-133.
[1]SL 317-2004 泵站安装及验收规范[S].北京:水利水电出版社,2005.[2]GB/T 8564-2003 水轮发电机组安装技术规范[S].[3]仇宝云.大型立式泵机组制造、安装质量对电机推力轴承运行的影响[J].大电机技术,1999(5):4-8.Qiu Baoyun.Influence of poor manufacturing and installating of a large vertical pump unit on working performance the thrust bearing[J].Large Electric Machine and Hydraulic Turbine,1999(5):4-8.(in Chinese)[4]江苏省江都水利工程管理处.江都排灌站[M].北京:水利电力出版社,1979.[5]《江都水利枢纽志》编纂委员会.江都水利枢纽志[M].南京:河海大学出版社,2004.[6]姜伟,仇宝云,问泽杭,等.大型水泵机组的维修性[J].排灌机械,2006,24(6):39-44.Jiang Wei,Qiu Baoyun,Wen Zehang,et al.Maintainability of large pump units[J].Drainage and Irrigation Machinery,2006,24(6):39-44.(in Chinese)[7]JB/T 10180-2000 水轮发电机推力轴承弹性金属塑料瓦技术条件[S].北京:水利水电出版社,2000.[8]杜刚海.大型泵站机组安装与检修[M].北京:水利水电出版社,1995.